Project Description: The project includes a walkway from the end of the Armour Street pavement to a T-shaped pier on Lake Davidson. Lake Davidson is considered part of Lake Norman, and all institutional and commercial installations on Lake Norman have to be approved by the Federal Energy Regulatory Commission.
Project Status: Project application has been submitted to the Federal Energy Regulatory Commission. Approval can take up to 1 year.
Page Updated: 9/24/20
TASK | DURATION (DAYS) | COMPLETION DATE |
Project application submitted to Federal Energy Regulatory Commission | October 30,2020 | |
FERC review | 360 | Monday, October 25, 2021 |
Construction drawings | 90 | Sunday, January 23, 2022 |
Mecklenburg County permitting | 60 | Thursday, March 24, 2022 |
Pre-bid meeting | 14 | Thursday, April 7, 2022 |
Bids due | 14 | Thursday, April 21, 2022 |
Contract signed | 14 | Thursday, May 5, 2022 |
Notice to proceed | 7 | Thursday, May 12, 2022 |
Construction complete | 60 | Monday, July 11, 2022 |